Select Sands – Resource Calculation on Bell Farm Property

Select Sands Corp (TSXV:SNS)(OTCQX:SLSDF) announced that the Company has completed a National Instrument 43-101 (“NI 43-101”) resources calculation on its Bell Farm Property (“Property”). The report dated April 4, 2017 was prepared by Elliott A Mallard, P.G. of KLEINFELDER, Jacksonville, FL, USA. The NI 43-101 Inferred Mineral Resources are 49,622,003 tons. A copy of the report will be filed under the Company’s profile on www.sedar.com.

  • The Bell Farm property covers 457 acres, has paved road access and available three-phase power.
  • The new property is located about 2 miles northwest of the Company’s existing Sandtown project.
  • Sandtown is currently producing finer mesh Northern White sand (40/70 and 100 mesh) and in February of 2016 completed a NI 43-101 resource calculation with 41.98 million tons of Indicated Mineral Resources.

Geology and Mineralization:

The deposit consists of the middle Ordovician-aged St Peter Sandstone, generally a massive bedded, medium- to fine-grained, well-rounded, friable, white sandstone. Forty (40) NQ diameter core holes have been drilled on the Property in three (3) separate drilling programs (October 2011, November 2012 and March/April 2014). Sieve analyses indicate a grain size distribution of 23.5% of 30/50 mesh, 48% of 40/70 mesh and 42.1% of 100 mesh (70/140 mesh)*. Average thickness of the sandstone on the Property is 48.9 feet (ranging from 1 foot to a maximum thickness of 108 feet on the Property). Samples submitted to Stim-Lab (a Core Laboratories Company) for quality analysis returned results that met or exceeded ISO 13503-2:2006/API RP19C:2008 standards.

*sum is greater than 100% due to overlap.

Zig Vitols, Select Sands Corp. President & CEO, stated, “With the increasing quantity of quality material becoming available to the Company, Select Sands has experienced major strides in a short period of time. The Bell Farm acquisition represents another milestone in building the foundation for the Company’s goal to become a top tier supplier of frac sand in the energy sector.”

Elliott A. Mallard, PG of Kleinfelder is the qualified person as per the NI-43-101 and completed the mineral resource estimate for the Bell Farm property and has reviewed and approved the technical contents of this news release.

Cautionary Note: Mineral resources that are not mineral reserves do not have demonstrated economic viability and there is no certainty that this preliminary economic assessment will be realized. The Company advises that the production decision on the Sandtown deposit referenced herein was not based on a feasibility study of mineral reserves, demonstrating economic and technical viability, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure. There is no guarantee that production will occur as anticipated or that anticipated production costs will be achieved. The Company further cautions that it’s previously disclosed preliminary economic assessment is preliminary in nature. No mining study has been completed. Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that the preliminary economic assessment will be realized.